MAISD Annual Web ReportMAISD Logo Icon

Contract Modifications
 

2018-19 Contract Modifications:

Enviro-Clean Services

Contracted Services: Custodial Services
Purpose of Modification: Staff wage cost of living adjusments
Original contract amount: $308,360
Additional contract cost: $2,345
Revised contract total: $310,705

Explorers Learning Center

Contracted Services: Operate Great Start Readiness Programs
Purpose of Modification: One-month cash advance to be repaid between June 1-August 15, 2019
Original contract amount: $243,523
Additional contract cost: $25,000
Revised contract total: $268,523

Kent Intermediate School District

Contracted Services: Hosting PowerSchool Special Education Software
Purpose of Modification:  Usage was greater than initial estimate
Original contract amount: $45,359
Additional contract cost: $18,687
Revised contract total: $64,046

 

 

Go to MAISD Annual Web Report - Table of Contents